|
|
|---|
|
Current Projects | |||||
|
| |||||
|
Past Projects University of Tennessee STP supply chain audit. The STP focuses on completing a production lead time. The project recommendations are to: 1. conduct a lean analysis of acquisition lead time to reduce the time from “need to PO” by at least 50 percent 2. prioritize the Johnson Outdoors Standardization STP in order of return on investment, with the highest return concepts implemented, 3. add buffer stocks for key components in specific places in the supply chain, 4. conduct a return on investment analysis for subsidized training of a temporary workforce, 5. conduct a lean analysis of tent manufacturer facilities that will reduce non-value added waste by 30 percent (with co-investment by the tent manufacturers), 6. evaluate assisting tent manufacturers purchase certain capital assets such as frame fabrication and welding equipment in a fair and balanced manner across the manufacturers ,7. complete work needed to obtain approval for an on-going program of minimum sustaining rates, and 8. implement a production and inventory planning system within tent manufacturer operations, with co-investment by the tent manufacturers. The team developed a sample banking strategy for the coated fabric supply chain. As part of the analysis, they found the largest risk in this supply chain is that there is only one producer of yarn for this application. The team recommends the DLA conduct a study to determine what it would take to establish another domestic manufacturer of yarn to reduce the risk. The team also conducted a component supplier lead time analysis to identify how the degree of a surge impacts lead time, where in the supply chain buffer stocks should be used and how much of an investment is needed. Lead time for a 50 percent surge is 12-15 weeks for the first shipment of fabric to the manufacturers, and grows proportionately with the surge percent increase. The team recommended the 3-4 weeks for weather testing of each lot be examined for potential elimination or adjustment. The examination would need to identify any cost savings for eliminating the testing requirement in addition to lead time reduction. Jim Vitrano, DLA, is working with USIFI to move away from lot by lot testing to frequency testing to address the testing issue. The team identified uncoated fabric as the best location in the supply chain to reduce lead time. and recommended developing a 30-day inventory bank for 100 percent surge conditions. However, when the bank is used, a 18-19 week lead time will still exist before the supply chain can ramp up to the new production levels. Uncoated fabric again was found to be the best location to create the additional bank. The costs in the presentation do not include warehouse costs, just inventory cost. The participants felt most fabric manufactures have the space to store the bank. Terri Scheetz, DLA, noted a banking analysis was conducted for the clothing and textile industry that provided recommendations to reduce acquisition lead time by 30 percent. The industry is making a concerted effort to implement the suggestions and meet the reduced lead time goal. While a buffer bank is a successful, it is a quick solution to lead time and should always be viewed as the last solution to reduce lead time. For example, are there alternate fibers or yarns that meet the MIL SPECS that can be used? Participants noted other suppliers are capable of making the fabric but choose not to. A waiver from the Berry Amendment is not a viable alternative. The temporary workforce is feasible to meet surge requirements. However, it takes a significant lead time to put in place the workforce, including finding available labor. STANDARDIZED Component Assemblies The objective of the proposed program is to identify, evaluate, and recommend component assemblies standardizations for the DSCP and COTS shelters for improved supply chain performance. They have found the MIL SPEC drawing package details are not documented and are being lost. The team feels the best way to create them is to reverse engineer. The team has been working on standard subassembly conceptual designs for wrappers, windows, ECU feed threws and vents. The analogy was made that each Service could have separate shirt pocket size requirements that differ only 1/8 of an inch from each other. This requires different templates and greater costs and assembly. By comparing the designs and requirements, the Services developed one standard shirt design that meets all of their needs. The same should be done for MIL SPEC tents. By moving from detail spec to performance spec should help resolve some of these discrepancies, leading to more standardization. Proposed Next Steps The proposed next steps for the Johnson Outdoors STP on Standardized Component Assemblies.The STP report, which sought to establish the feasibility of standard component assemblies, is finalized; contact Leo Plonsky for a copy.
In order for the government and industry to move forward, the next steps should be to: (1) Johnson conducted a seam sealing test using three different fabrics to evaluate the reliability of bonds between different materials from different manufacturers. The tests were conducted on Johnson equipment; the results showed different materials can be sealed to each other. Though more study needs to be done,including a round-robin test across manufactures equipment and input from fabric manufactures – it is encouraging that it could work. (2) (3) (4) (5) JOCOTAS will need to provide support for this. JOCOTAS should maintain ownership of the drawings. (6) | |||||
|
|